Using the OOB Rally integration to create Programs in Rally and sync Rally data back to the Clarity Program. Trying to sync data back to Clarity from Rally the processes does not process the data back into the Program in Clarity.
Release : 16.1.0
Entered the Planned End Date value in Rally and then the sync worked.