Rally - Some Key Results not included in the Next Interim Target Key Result Progress bar
search cancel

Rally - Some Key Results not included in the Next Interim Target Key Result Progress bar

book

Article ID: 259921

calendar_today

Updated On:

Products

Rally SaaS

Issue/Introduction

Occasionally some Key Results seem to not be included in the Next Interim Target Key Result Progress bar at the top of the Objective page.

 

Environment

Release : SAAS

Resolution

When interim target dates are configured for an OKR, the progress calculations only use the next upcoming interim date and only if it has an interim value configured for it.  If a key result doesn't have an interim value configured for the next interim date, then that key result is excluded from the calculation.