On a project with the Set Planned Cost Dates attribute checked, creating and deleting a Cost Plan makes the attribute to be unchecked.
Steps to Reproduce:
Actual Results:
Actual Results:
Now, when trying to edit Planned Cost, an error will be displayed: INV-0016: Missing Planned Cost Start or Planned Cost Finish date
This is working as designed.
After removing the Cost Plan, it resets the fields and you can then enter the data. For the manual update, the dates must be filled in before you set the cost amounts so that it knows how to spread the amount.