Some Timesheet actuals are missing in MUX Staffing Grid
search cancel

Some Timesheet actuals are missing in MUX Staffing Grid

book

Article ID: 258699

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

SUMMARY: There are some resources whose timesheet hours are not showing on the Staffing Module Grid as well as the Staffing page on the Investment.

Steps to Reproduce: 

1. Post Timesheets
2. Go to the Staff Grid and configure Per-Period-Metrics for Actuals for the appropriate period

Expected Results:  All actual hours from timesheets show on the Staff Grids

Actual Results:  Certain resource's hours are not showing on the grids.


Workaround: It appears that updating the assignment will then trigger the values to show.  

Environment

Release : 16.1.0

Cause

DE68169

Resolution

Fixed in 16.1.1