Can you add an milestone from an external Project?
search cancel

Can you add an milestone from an external Project?

book

Article ID: 258464

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

Can you please confirm me how to add an external milestone from project A to project B in the new UX ?

This external milestone should be in read only access from project B.

Environment

Release : 16.0.2

Resolution

Not possible to add tasks from other projects/subprojects as milestones (they are beng added as proxy tasks)