Issue/Introduction

Need to know if we can xog the time period to update the finish date? Could you please advise.

Environment

Release : 16.0.0

Resolution

Once there are timesheets, you cannot modify it.

The only way is to delete that time period and it's associated timesheets so that new time reporting period can be created.