Rights Required to see all Action menu under Task Timeline View
search cancel

Rights Required to see all Action menu under Task Timeline View

book

Article ID: 258079

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

What are the rights needed to get those 3 actions under Task Timeline View :

  • Create tentative schedule
  • Auto schedule
  • Compare to Baseline

Environment

Release : 16.1.x

Resolution

Below rights are needed 

  • Project - Edit Management   
  • Project - Schedule In Browser    
  • Project Management - Tiles Navigate   
  • Project Management - Navigate