Error: "TMA-0401: The dates entered overlap an existing time period"
search cancel

Error: "TMA-0401: The dates entered overlap an existing time period"

book

Article ID: 257840

calendar_today

Updated On:

Products

Clarity PPM SaaS

Issue/Introduction

Receiving below error when trying to re-add a time period that was originally deleted.

"TMA-0401: The dates entered overlap an existing time period"

Environment

All

Cause

If Delete Investments and Time Reporting Periods job is not ran after confirming deletion it throws the error.

Resolution

1) Click Administration, Project Management, Time Reporting Periods.
2) Filter by Status for all Closed reporting periods.
3) Select the reporting periods and click Mark for Deletion.
4) Confirm the deletion.
5) The Marked for Deletion flag appears checked for the time period.
6) Run the Delete Investments and Time Reporting Periods job.