Copy Project Assignment Finish Date: Midnight Date - adds day
search cancel

Copy Project Assignment Finish Date: Midnight Date - adds day

book

Article ID: 257343

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

SUMMARY: Assignment dates can change by 1 day when copying project is the source assignment finish has the midnight date.


Steps to Reproduce: 

1. This is only applicable if you have midnight dates for the Finish on the assignment.
2. For an assignment that has a midnight finish date note the date
3. Copy the project
   - Check the finish on the assignment on the new project
    


Expected Results: Has the same finish date

Actual Results: Finish date is one day later (with 5 pm finish time)

Workaround: None

Environment

Release : 16.1.0

Cause

Reported as DE67973

Resolution

DE67973 Currently under engineering review.

 

Additional Information

Note:

In recent versions of Clarity (15.9.3 on) the assignment finish date defaults to 5 PM and cannot be changed to the midnight date.

There may be some old projects which have the midnight dates.  These are affected by the reported bug.