There are cost plans present in the ideas and projects that are being imported into a Roadmap. However, the following fields in the Roadmap Items do not have any data against them
Forecast Cost
Forecast Capital Cost
Forecast Operating Cost
Resolution
The fields being looked into are not the correct ones. Data entered into Cost Plans are made available in Roadmap Items against the following fields: