How to load a schedule job normally scheduled on a Saturday on a different date?
Component: ESP WORKLOAD AUTOMATION
Release: ALL
1. Go to ESP Main Menu to Events / Control an existing Event ( E.3)
2. Trigger the Event and update Trigger time using example -> 12.00.01 SAT 3 DEC 2022 and specify Y to hold APPL
3. Go to CSF and place LJE next to job and validate it has the correct scheduled date and time you want run from past.
4. Release the Job (AA)
This would be used if you needed to trigger job that should have scheduled in past so that all requirements are met within ESP.