Load ESP scheduled job once on a different date
search cancel

Load ESP scheduled job once on a different date

book

Article ID: 255549

calendar_today

Updated On:

Products

ESP Workload Automation

Issue/Introduction

How to load a schedule job normally scheduled on a Saturday on a different date?

Environment

Component: ESP WORKLOAD AUTOMATION 
Release: ALL

Resolution

1. Go to ESP Main Menu to  Events / Control an existing Event ( E.3)
2. Trigger the Event and update Trigger time using example -> 12.00.01 SAT  3 DEC 2022 and specify Y to hold APPL
3. Go to CSF and place LJE next to job and validate it has the correct scheduled date and time you want run from past.
4. Release the Job (AA)

Additional Information

This would be used if you needed to trigger job that should have scheduled in past so that all requirements are met within ESP.