When using the ROLL: N function on the CA 7 CPU JOB SCHEDULING PARAMETER EDIT (DB.2.1-E) screen, a SCHID should schedule even non-available scheduling days if applicable. However, when using the DAILY option on this screen, the ROLL: N does not work.
When you choose the DAILY option on the DB.2.1-E screen, a schedule is created for the job that matches the calendar used. No non-schedule days are considered.
If you want the job to run every day of the week regardless of whether it is available on this calendar, use ROLL: N and a WEEKLY schedule:
__ X __ WEEKLY SUN: X MON: X TUE: X WED: X THU: X FRI: X SAT: X