Actual Costs are not correct on Roadmap
search cancel

Actual Costs are not correct on Roadmap

book

Article ID: 252840

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

The following are not showing the correct values on the Roadmap view.  

  1. Total Actual Cost
  2. Total Capital Cost
  3. Total Operating Cost

 

Environment

Release : 16.0.3

Resolution

Running the "Post Actuals to Investment" job is required in order for the information to display in the Roadmap correctly. After running the job, resync the Roadmap data.

If the Actuals changes, the job will need to be rerun.