The Project Earned Value report is missing -
The data on the top half of the report is complete. The graph is charting that data, so why would the graphs and periods be missing
Release : 16.0.3
Update Earned Value History job had not been ran with all options checked
Verify the Earned Value periods exist
Make sure to run jobs -