Dates are Off for Item Synced by Rally Adapter for Jira (RaJ)
search cancel

Dates are Off for Item Synced by Rally Adapter for Jira (RaJ)

book

Article ID: 250652

calendar_today

Updated On:

Products

Rally SaaS

Issue/Introduction

When an item has been synced by the RaJ the date shifted by a day. For example:

When we update the "Planned Start Date and  Planned End Date" fields in Rally and trying to sync with Jira, adapter is parsing the start date as one day before.

 

Environment

Release :

Component :

Cause

The timezones are not aligned. 

Resolution

Check the timezones for Rally, the adapter, and Jira to make sure they align