The resource allocation and assignment report is starting the weekly periods in the report on Sunday in the timescale view. I have set the first day of the work week to be Monday in the project management settings area and have run the datamart and load datawarehouse job. However the weekly periods in the report continue to start on Sunday and not Monday.
Release : All supported releases
Component : Clarity Data Warehouse
For all weekly time slice requests, the From Date must be the same day as the First Day of the Work Week in the Project Management settings:
1. In Project Management Settings, set the start of the Work week to Monday.
2. Modify the weekly slices to start on Monday.
3. Run Load Datawareshouse full Load
The weekly reports should now have a start day of Monday