UIM ad_response probe is unable to start and showing in red error status in Infrastructure Manager client interface 

In logs can see error as MAX restart reached for the probe ad_response 

Environment

Release : Any supported UIM release 

Component : 1.80

Resolution

For ad_response probe 1.80 or later, installing .NET Framework version 4.8 is a prerequisite.