The following are steps to take to quiesce CA 7 job submission:
- Change the Initialization File (pointed to by the UCC7IN DD statement in the CA 7 online procedure) SCHEDULE statement to add STOPQ=YES prior to IPL or before restarting CA 7.
- After CA 7 is started issue these top line commands:
- HOLD,Q=REQ
- HOLD,Q=RDY
- SSCAN,SCAN=HLD - will place all jobs that will enter the the queues in a HOLD status
Then when ready to start job submissions:
- START,Q=REQ
- START,Q=RDY
to get the jobs ready to submit....at this time you can release (post the hold requirement) job by job or isssue:
- RELEASE,Q=REQ
- RELEASE,Q=RDY
- SSCAN,SCAN=REL - to stop the hold requirement being added to jobs as they enter the queues.