The task is to use Migration Xpress utility to migrate data and configuration to the new cluster.
However, it seems Migration Xpress doesn't migrate schedule jobs of Cleanup Submitted Tasks task.
Can we migrate schedule jobs using Migration Xpress?
Release : 14.4
Component : IdentityMinder(Identity Manager)
The schedule jobs for Tasks are not contained in IM Environment, but IM scheduler database. The tasks are contained in IM Environment, but not the schedule jobs for the tasks. Because of that, those schedule jobs cannot be migrated using Migration Xpress.
When upgrading vApp, we can use Gradual Migration approach to avoid this issue. Specially for vApp to vApp migration, the recommendation is to utilize Gradual Migration instead of Side-by-Side Migration (using Migration Xpress utility) approach.