Started task BUNLSRT1 receives multiple dynamic allocation errors with all reports coming and their BUNDLSER for Bundl abended for several hours.
----
LDM0418E Dynamic allocation of ddname dataset failed; R15=0004,error code=0210
-----
Started task: BUNDLT1
BND7009E Job abended - return code S000 - U600
BNDL769: ERROR ON RETURN FROM DPMB006 ATTACH.
Release : 5.0
Component : Bundl
Regarding generation of the LDM0418E message, the client found that there is a backup job that runs backups for two L-SERVs, that run in another LPAR on the same sysplex, that were holding the BUNDL VSAM files:
xxxxxxxx.BUNDL.DPM*
The procedure was:
. Stop the second L-SERV.
. Allow the backup job to finish.
. Start up the two L-SERVs and two BUNDLs.