'exception processing NkCurve attribute' error

book

Article ID: 244001

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

When the Task is created in Modern UX, it is using the Studio default values for Current Day/Time for both Start and Finish Dates, the user is not able to enter a value into the Assignment ETC time-varying Grand Totals field. 

Steps to Reproduce:

  1. Log into the Modern UX
  2. Create project that uses a blueprint that includes the modules Task, Staff and Assignments
  3. Click on the Staff view of the project created in step 1, click the '+' button to add a new resource and set both the Start and Finish dates to the current day
  4. Click the Task view and create a new task with a Start and Finish value of the current day
  5. Click on the Assignments view, click the view options. Ste the Periods to Months, Per-period Metrics to Actuals and ETC
  6. Still in the Assignments view ensure that the Columns Panel Grand Totals are ticked for Actuals and ETC.
  7. Still in the Assignments view click on '+' button, add the task created in step 4 then add the resource from step 3
  8. Attempt to enter a value in either the Grand Totals Actuals or ETC

Expected resuls: A value can be added.

Actual results: There is popup message.

Environment

Release : 16.0.1, 16.0.2

Component : Clarity MUX UI Usability

Cause

This has to do with the Start and Finish date being the same time in MUX.

In Classic the Start is normally 8 AM and Finish is 5 PM. However in MUX this is not the case and there may be no duration  and therefore cannot have a total value.

This has been logged as DE65432.

Resolution

This issue is fixed in Clarity 16.0.3.