Timesheets Showing all Tasks not Just Assigned Tasks

book

Article ID: 242829

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

How can we easily find tasks which we are assigned but have 0 ETC.  Many times non project work such as Other Work has 0 allocation and assignments.  Once time is posted to these the status of the assignment becomes complete and they do not show when you Add Assigned Tasks.

You will need to click on Select Tasks which brings back a list of Open for Time Entry Tasks for projects where you are assigned.

This will bring back all tasks which can be added to your timesheet, if you are assigned or not.

 

Environment

Release : 16.0.1

Component : Clarity Time Management

Resolution

Use the Smart Filter on the Select Tasks option to make 

Assigned Resources = Current User

This can be saved as your default filter so each time you go to Select Tasks it will only show the tasks you are assigned to.