ALERT: Some images may not load properly within the Knowledge Base Article. If you see a broken image, please right-click and select 'Open image in a new tab'. We apologize for this inconvenience.

Does Cost Plan Details allow Auto Start process?

book

Article ID: 241447

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

Is it possible to initiate (auto Start) a process when an update is made to a line item in the Cost Plan Details?

Resolution

Auto Start a process against Cost Plan Details is not possible because it cannot be selected as a Primary object in the process definition.