Does Cost Plan Details allow Auto Start process?
book
Article ID: 241447
calendar_today
Updated On:
Products
Clarity PPM SaaSClarity PPM On Premise
Issue/Introduction
Is it possible to initiate (auto Start) a process when an update is made to a line item in the Cost Plan Details?
Resolution
Auto Start a process against Cost Plan Details is not possible because it cannot be selected as a Primary object in the process definition.