When building Uproc launch conditions on a recently upgraded Dollar Universe node, the process dependency condition and the entire Processing Date section of the dependency conditions are grayed out. Processing Date options for dependency cannot be changed.
How can this issue be fixed?
Release : 6.10
Component : DOLLAR UNIVERSE
Make the following changes should resolve the problem:
- Change Functional period from "none" to "Daily"
- Change Uproc memorization as an event from "No memorization" to "memorize a single instance for a processing date"