ALERT: Some images may not load properly within the Knowledge Base Article. If you see a broken image, please right-click and select 'Open image in a new tab'. We apologize for this inconvenience.

New UX : Staffing Plan Totals don't get updated after a series of updates to the projects

book

Article ID: 241052

calendar_today

Updated On:

Products

Clarity PPM On Premise

Issue/Introduction

Staffing Plan totals for a resource don't get updated after a series of updates in New UX.

STEPS TO REPRODUCE: 
1. Take a large enough Customer, having around 5K resources.
2. Login to new UX.
3. Navigate to Staffing Plan.
4. Click on Investments - Resources to bring up the investments view.
5. Take an investment with around 100 resources assigned.
6. Modify the allocation for a resource for a month, wait for 2 secs, press tab and then edit the allocation for next month.
7. Repeat Step 6 4-5 times.

Expected Results :- The Totals Field of the resource should get updated with the Allocation totals of the resource for this investment.
Actual Results :- The totals stop updating after a few tries. 

Environment

Release : 16.0.2

Component : Clarity New UX Usability

Resolution

This is taken in as Defect DE64991 and is under engineering review.

Workaround is to refresh the page.