Converting an idea to project in MUX increments the finish date by 1 day

book

Article ID: 241033

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

When converting an idea to a project, the finish date is incremented by one day in the Modern UX. The same action in the Classic UI respects the idea dates

STEPS TO REPRODUCE:
1. Create an idea in Classic UI.
   Start date: 02/05/22
   Finish Date 05/05/22
2. Submit the idea for approval and Approve it
3. Convert the idea to a project
4. Note the resulting dates of the project created
   They match the idea dates
5. Move to the Modern UX
6. Select the same idea and Convert it to a project
7. Note there is a pop-up with idea default dates displayed.
8. Leave the default dates or change them to any other ones
   Note the dates on the screen

Expected Results: The project dates to be the default idea dates or the ones set when converting the idea to a project
Actual Results: The start date is OK. The finish dates has been incremented by a day to 06/05/22

Cause

This is caused by DE64989

Resolution

This is currently being analyzed by Engineering