Issue/Introduction

Is there a way to set WBS level when adding a task in the Modern UX? For example, we usually use Workbench and the WBS structure is

Phase (WBS level 1)

   Activity (WBS level 2)

      Task (WBS level 3)

When I add a task in MUX, either on the Gantt or on the Task tab, it says it's a task but the WBS level is 1. We would like to set it to 3, and move it under a Phase/Activity to preserve our WBS structure

Environment

Release : 16.0.1

Component :

Resolution

There is a WBS field ie the timeline view of MUX, Go to Project and click on Tasks module and you have 3 choices for Views: Grid, Board and Timeline so this is Timeline view where you click to be able to see WBS.