ALERT: Some images may not load properly within the Knowledge Base Article. If you see a broken image, please right-click and select 'Open image in a new tab'. We apologize for this inconvenience.

Create from Template: Task Critical attribute not copied

book

Article ID: 239789

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

New from Template does not copy the Task 'Critical' attribute boolean correctly


Steps to Reproduce: 

  1. Log into the Classic UI
  2. Add the Critical to the Task object's properties view 
  3. Create a new project or use an existing 
  4. Create a task and toggle the 'Critical' attribute to on in properties view.
  5. Save and return out of the task
  6. Save project as template
  7. In Modern UX or Classic UI click the New from Template button
  8. Select the project template create in steps 3-6.
  9. Open the newly created project and view the tasks 


 
Expected Results: The task critical attribute is ticked

Actual Results: The task critical attribute is not ticked

Cause

DE64429

Environment

Release : 16.0.1

Component : Clarity Project Management

Resolution

Resolved in 16.0.2 

Additional Information

Note: This works for other boolean attributes such as Fixed Duration, Open for Time Entry, Key Task Has Subtasks and Has Assignments