View Password Request reports invalid date range at Privileged Access Manager (a.k.a PAM) 4.0.2a.
It shows advanced 1 year from a specific Start Date / End Date.
This problem is occurred on between Dec 26 and Dec 31 at Start Date / End Date.
And also, this problem is occurred at another report which has Start/End Date.
for Example,
Start Date: 2021/12/26 / End Date: 2021/12/31 and run report.
It shows 2022/12/26 to 2022/12/31 at Date Range.
Release : 4.0
Component : PRIVILEGED ACCESS MANAGEMENT
This problem is occurred after 4.0.2a.
Also, this is known problem and fixed.
It will fix in next release, 4.0.3, 4.1 or later.