Project Actuals Not Updating in Modern
book
Article ID: 239601
calendar_today
Updated On:
Products
Clarity PPM On Premise
Clarity PPM SaaS
Issue/Introduction
The Actual Cost field does not get updated in Modern > Project > Tasks.
They do appear in the Classic.
Resolution
After Actuals are posted via the 'Post To Wip' job, proceed to run the latest additional job(Post Actuals to Investment).