Issue/Introduction

Currently getting four hours interval of utilization graph in daily scheduled report for last 24hrs/days through OC.

Requirement is for 1 hrs interval graph of utilization on daily scheduled report of last 24hrs/day.

 

 

 

 

 

 

Environment

Release : 20.3.3 /20.4.x

Component : Report Scheduler

Resolution

Can  change the aggregation interval to 1 hour in the scheduled report template 

https://api-broadcom-ca.wolkenservicedesk.com/attachment/get_attachment_content?uniqueFileId=mJ7a67oAeiS+bGwJZ9wKzQ==

You can select different aggregation intervals depending on the requirement

 

Additional Information

Working with Report Scheduler