Summary: In Classic, the user can get confused if they use an action and cannot navigate correctly through the menu afterwards.
Steps to Reproduce:
Expected Result: You can edit the time scaled values.
Actual Result: You cannot edit.
Note that the Start and Finish Dates show -- -- instead of the correct dates.
Release : 16.0.0, 16.0.1
Component : CLARITY PROJECT MANAGEMENT
DE64207
Resolved in 16.0.2