When entering 'Cost' information in a cost plan, the toaster message shows:
TSV type attribute 'cost' cannot have segment dates beyond the curve start or finish dates
APP log shows error:
Exceptioninfo: could not update resource. Resource Name: costPlanDetails. Error code validation.api.segmentDatesBeyondCurveDates. TSV Type attribute cost can not have segments beyond the curve start and finish dates.
The View Options Period will need to match the cost plan period type.
Go to the View Options to make sure the types are correct.
The cost plan period types will need to match.
For example, if the cost plan period type = Month, the View Options Period will also need to = Month to edit the cost.