In the SSM Activation Panel, specify "PREREQUISITE RESOURCES" (the names of resources that need to be activated/started before the resource can be started). Is it possible to specify more than one of these PREREQUISITE RESOURCES?
Environment
Release : 14.0
Component : OPS/MVS
Resolution
Possible to specify multiple resources to PREREQUISITE RESOURCES.