Can not start trellis, start after probe not enabled () after upgrade to UIM 20.4
search cancel

Can not start trellis, start after probe not enabled () after upgrade to UIM 20.4

book

Article ID: 233412

calendar_today

Updated On:

Products

DX Unified Infrastructure Management (Nimsoft / UIM) CA Unified Infrastructure Management SaaS (Nimsoft / UIM) Unified Infrastructure Management for Mainframe

Issue/Introduction

After upgrading trellis will not start ad throws an alarm. "Can not start trellis, start after probe not enabled ()"

Environment

- UIM 20.4

Cause

- dependencies

Resolution

Check the state of the dependent probes for trellis. The services in trellis have dependencies on the following probes:

  1. data_engine
  2. ems
  3. nas
  4. udm_manager

Make sure to correct any issues with these probes before restarting trellis.

Additional Information

Trellis is no longer supported on the latest version of 20.4.