Can not start trellis, start after probe not enabled () after upgrade to UIM 20.4
book
Article ID: 233412
calendar_today
Updated On:
Products
DX Unified Infrastructure Management (Nimsoft / UIM)
CA Unified Infrastructure Management SaaS (Nimsoft / UIM)
Unified Infrastructure Management for Mainframe
Issue/Introduction
After upgrading trellis will not start ad throws an alarm. "Can not start trellis, start after probe not enabled ()"
Resolution
Check the state of the dependent probes for trellis. The services in trellis have dependencies on the following probes:
- data_engine
- ems
- nas
- udm_manager
Make sure to correct any issues with these probes before restarting trellis.
Additional Information
Trellis is no longer supported on the latest version of 20.4.