In the Roadmap Timeline View, the metrics are not displaying correctly.
In the Grid view, it shows as $1000, but instead of showing $1K in the Timeline view, it shows $1 (missing K).
Steps-To-Reproduce:
1. Go to Home > Account Settings and Locale to United States. Click Save.
2. Go to the Roadmap instance having the issue.
Review the value = $10K
3. Go back to Account Settings to set Locale to French(Canada). Click Save.
4. Go back to the Roadmap instance having the issue.
Review the value = $10 (10 instead of 10k)
Expected: The value should not drop the K, denoting thousands.
Actual: The value drops the K which changes the value significantly.
This is only reproducible in versions lower than 15.9.3.
This is an unidentified issue not reproducible in 15.9.3+.
The supported resolution is to upgrade to the latest available version of Clarity.