Need to sync Planned Cost field and Status comment field from Initiative to Roadmap but we cant able to do it. Can you please help to know is there a possibility to do it.
Release : 16.0.0
Component : Clarity Roadmaps
The planned cost fields are just called Costs on the Roadmap Items vs Planned Costs on the Investments.
You will see Capital Cost and Operating Cost as the fields to Sync.
For the Status Comment, that field is not available to add to the Roadmap Items at this time.