How to define an Event to run Quarterly
search cancel

How to define an Event to run Quarterly

book

Article ID: 23194

calendar_today

Updated On:

Products

FAQS - Automated Systems Operation

Issue/Introduction

Since there is not an event day in FAQS PCS for quarterly, how to set up an event for quarterly processing without creating 4 separate events?

 

 

Environment

Release: 5.1 
Component: FAQS-Automated Systems Operation

Resolution

Set up a CYCLE with the 4 dates needed.
The dates can be the first or last day of the quarter.

From the PCS main menu select: O Configuration Options
Followed by: F Define Holidays and Cycles
From this menu, select: C Cycle Definition List by IDs
Select PF4 ADD
Choose a new3 digit numeric ID and press enter.

This example uses Jan 3, April 1, July 1 and October 1 as static cycle end dates
  ** in the year means run every year.

 Cycle Id ===> 004     Desc ===> Quarter End Dates      
    Date range for cycle period                         
     YY/MM/DD           YY/MM/DD                        
??????????????????????????????????? ??????????????      
(01) **/01/03   <===>   **/01/03                        
(02) **/04/01   <===>   **/04/01                        
(03) **/07/01   <===>   **/07/01                        
(04) **/10/01   <===>   **/10/01 

Define an event that will only run on these dates

Then define 1 event that uses this cycle

                                                           
Event Name  ===> QUARTEVT              Group Name  ===>    
Description ===> quarter end           Event Hold  ===> N  
Event CPUid ===> nnnnnn                ABND RC     ===>
Command     ===> qbatch.jcl                                                
CSPD        ===> ____                  Target Node ===>          
Early Time  ===> 0900                                            
Late Time   ===> 2400                  Max Run Time ===> 000     
Abort Time  ===> 2600            XDATE OR ?  MTWTFSS   CYCLE<=== 
Event Day   ===> CYCLE <--        ___  _  _  _______   004