Since there is not an event day in FAQS PCS for quarterly, how to set up an event for quarterly processing without creating 4 separate events?
Release: 5.1
Component: FAQS-Automated Systems Operation
Set up a CYCLE with the 4 dates needed.
The dates can be the first or last day of the quarter.
From the PCS main menu select: O Configuration Options
Followed by: F Define Holidays and Cycles
From this menu, select: C Cycle Definition List by IDs
Select PF4 ADD
Choose a new3 digit numeric ID and press enter.
This example uses Jan 3, April 1, July 1 and October 1 as static cycle end dates
** in the year means run every year.
Cycle Id ===> 004 Desc ===> Quarter End Dates Date range for cycle period YY/MM/DD YY/MM/DD ??????????????????????????????????? ?????????????? (01) **/01/03 <===> **/01/03 (02) **/04/01 <===> **/04/01 (03) **/07/01 <===> **/07/01 (04) **/10/01 <===> **/10/01
Define an event that will only run on these dates
Then define 1 event that uses this cycle
Event Name ===> QUARTEVT Group Name ===> Description ===> quarter end Event Hold ===> N Event CPUid ===> nnnnnn ABND RC ===> Command ===> qbatch.jcl CSPD ===> ____ Target Node ===> Early Time ===> 0900 Late Time ===> 2400 Max Run Time ===> 000 Abort Time ===> 2600 XDATE OR ? MTWTFSS CYCLE<=== Event Day ===> CYCLE <-- ___ _ _ _______ 004