Unable to edit Resource Allocation for Other Work instances
search cancel

Unable to edit Resource Allocation for Other Work instances

book

Article ID: 231782

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

A Project Manager is unable to edit Resource Allocation for Other Work instances.

When he goes to the Resource Allocation > Details tab for a specific resource, he can edit the allocation cells for projects, but not for other work instances.

The Project Manager does have all Resource Booking rights. Is there any specific access right required?

Cause

The Project Manager does not have any Other- Work related access rights.

Resolution

Resource Booking rights are required in order to modify the resource allocation.

Additionally, in order to edit allocation for Other Work instances, the minimum access needed is Other Work - Approve - All