Task Timeline View does not recognize URL fields
search cancel

Task Timeline View does not recognize URL fields

book

Article ID: 231166

calendar_today

Updated On:

Products

Clarity PPM On Premise

Issue/Introduction

SUMMARY: URL field on Task Timeline view is not recognized as URL in 15.9.3 and 16.0

STEPS TO REPRODUCE: 

1. Create URL type attribute on the Task object and make it API enabled.
2. Navigate to Modern UX
3. Go to project nd click on Tasks tab.
4. Click on Timeline view and add URL attribute created in Step 1
5. Notice it is not recognizing it as URL type since you can't click on it.

Expected Results: It should recognize it as URL type.

Actual Results: It does not recognize as URL type.

Environment

Release : 15.9.3

Component : Clarity MUX UI Usability

Resolution

DE63548, Fixed in 16.0.2, 16.0.1.1 and 15.9.3.4.