Cannot update the duration of Task in the New UI

book

Article ID: 230533

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

For every single project when the duration is changed through the Grid the data is not getting updated, it reverts back.

 

 

Environment

Release : 15.9.x, 16.0.x

Cause

The Duration field cannot be manually adjusted. The value is automatically populated based on the duration of days from the Start to the Finish of the Task.

For example, if the Task's Start is January 2, and the Task's Finish is January 3, the Duration will be "2". If the Finish date is changed to January 4, the Duration will automatically change to "3".

Resolution

The Duration field cannot be manually adjusted. The value is automatically populated based on the duration of days from the Start to the Finish of the Task.

For example, if the Task's Start is January 2, and the Task's Finish is January 3, the Duration will be "2". If the Finish date is changed to January 4, the Duration will automatically change to "3".