Select 'Copy time entries from previous timesheet' on the Timesheet Options page, on a new timesheet click 'Populate'. Tasks added into the new timesheet include not only the ones from the previous timesheet, but also ones that the resource is currently assigned to, open for time entry, and have non-zero ETC. Is this a defect?
This is per the current design.