Weekly Period Type is not available while creating/updating Cost Plans under Financials module

book

Article ID: 229588

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

In Modern Ux, Weekly Period Type is not available while creating/updating Cost Plans, however, you get to choose Per-Period metrics (TSVs) to be viewed by any time period type (Monthly/Quarterly/Annually) including weekly

 

STEPS TO REPRODUCE: 

  1. Login to clarity with appropriate rights
  2. Navigate to projects and create/update a cost plan
  3. While creating cost plan, for the attribute Period Type there is no option to select Weekly Period Type
  4. Choose any of the period type and create/update the cost plan
  5. Now navigate to the instance of the cost plan created in the above steps and create a per period metrics and in that weekly periods is seen

Expected Results: User should be able to select weekly period during creation/editing of cost plan 

Actual Results: User doesn't have option to select weekly period type

 

 

Environment

Release : 15.9.3,16.0.0

Component : CLARITY STUDIO

Cause

This is a defect DE63345

Resolution

The defect DE63345 is fixed in 16.0.1