When the Event has both SCHEDULE and NOSCHED statements, "NEXT DUE" on the Event panel shows the wrong schedule date, and E.5 shows the correct date.
Release : All
Component : ESP WORKLOAD AUTOMATION
"NEXT DUE" shows the date/time based on the SCHED setup, and ESP will bypass it if there is a NOSCHED for same date/time.
Example:
13.38.00 TUE 23NOV21 ESP6108I EVENTEX: CYBER.AGENT scheduled
13.38.00 TUE 23NOV21 ESP6124I EVENTEX: CYBER.AGENT execution bypassed due to NOSCHED request
So E.5 shows the proper information while E.3 display is based on the SCHEDULE statement.
You can also use the NEXT command from pagemode to display the next event executions.