The Finish [date] value is cutoff in the grid, and the task widget does not seem to properly auto-adjust the width of date columns to show the full date value (rather it cuts off the date values). How can you increase the column width of Finish to show the full date value?
Expected Results: The full date appears for both the Start and Finish date fields (IE Aug, 31, 2021)
Actual Results: The dates are cut off and display with at least the last 3 digits cut off (IE Aug 31, 2…)
Release : 16.0.0
Component : CLARITY PROJECT MANAGEMENT
DE63257. This happens if your zoom level is 100% or higher.
This is fixed in 16.1.1