Issue/Introduction

SUMMARY: 

In the MUX, when going to the Staff Planning, when you view the available fields, duplicate labels display.

STEPS TO REPRODUCE: 

1. Log into the MUX, and go to the 'Staff Planning' icon
2. In the lower 'Requests' section hover over the value header values, and a hamburger menu icon displays. Click the icon.
3. Click the tiles icon (on the right). Notice 'Allocation' and 'Hard Allocation' displays multiple times
4. If you select all the values, different numbers may display.

Expected Results: 

In previous releases only a single value would display

Actual Results:

Multiple values display, and it's not clear what the difference of these values are.

Environment

Release : 15.9.3

Resolution

Each value is actually not a duplicate, but showing different information. There are three different values, because there are three different "Work Effort Units of Measurement" returned.

The first item is related to "Hours". The second is "FTE". The third is "Days".

DE63224 has been logged, and is being reviewed by the Product Development team.