Classic UX - Resource - Allocations - Detail inconsistent allocation bar. 

book

Article ID: 227221

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

For some resources that have more than 100% allocation for a time period, the display of the bar graph is inconsistent.

 

Environment

Release : 15.9.3

Component : CLARITY RESOURCE MANAGEMENT

Cause

DESCRIPTION FOR RELEASE NOTES: 

 

SUMMARY: Classic UX - Resource - Allocations - Detail inconsistent allocation bar. 

 

STEPS TO REPRODUCE: 
1. Login to classic as an Admin or Resource Manager 
2. Home, Resources, Select a resource 
3. Allocations Tab, Drop Down, Detail 
4. Review the allocations 
5. Modify Allocation Period to be 100% 
6. Modify the next Allocation Period to be 150% 
7. Modify the next Allocation Period to be 50% 
8. Gear, Configure 
9. List Column Section Tab > Options 
     HIGHLIGHT ROW BY ATTRIBUTE   =  "Allocation"
  Work Effort Unit of Measure = "FTE"
10. Under  "Column and Bar Graph Summary", click "Aggregation Row" > "Allocation By Period"
   THRESHOLD LINE ATTRIBUTE = Unused Allocation 
   THRESHOLD AGGREGATION FUNCTION = Sum 
   Over-Threshold Color = Blue 
   Save 
11. On the Resource Allocation Detail tab, the Allocation By Period bar graphs are inconsistent.  

    150% takes up the whole bar (expected)
    100%  bar for the next period does not take up the whole space
    50% bar seems to take less than a third of the space

 

Expected Results: Allocation bar is displayed accurately and consistent. 

Actual Results:  Allocation bar is inconsistent in its display. 

Workaround: The numbers are still there, so this is easy to workaround. 

 

 

 

Resolution

This is working as designed.

Across the same row, the height of all bars are RELATIVE to the MAXIMUM value. 

if you tried 200%, 150%, 100%, 50% -  expect it to show across the row the colored amount HEIGHT at 100%, 75%, 50%, 25% of the row height