Classic UX - Resource - Allocations - Detail inconsistent allocation bar. 

book

Article ID: 227221

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

For some resources that have more than 100% allocation for a time period, the display of the bar graph is inconsistent.

 

Cause

DESCRIPTION FOR RELEASE NOTES: 

 

SUMMARY: Classic UX - Resource - Allocations - Detail inconsistent allocation bar. 

 

STEPS TO REPRODUCE: 
1. Login to classic as an Admin or Resource Manager 
2. Home, Resources, Select a resource 
3. Allocations Tab, Drop Down, Detail 
4. Review the allocations 
5. Modify Allocation Period to be 100% 
6. Modify the next Allocation Period to be 150% 
7. Modify the next Allocation Period to be 50% 
8. Gear, Configure 
9. List Column Section Tab > Options 
     HIGHLIGHT ROW BY ATTRIBUTE   =  "Allocation"
  Work Effort Unit of Measure = "FTE"
10. Under  "Column and Bar Graph Summary", click "Aggregation Row" > "Allocation By Period"
   THRESHOLD LINE ATTRIBUTE = Unused Allocation 
   THRESHOLD AGGREGATION FUNCTION = Sum 
   Over-Threshold Color = Blue 
   Save 
11. On the Resource Allocation Detail tab, the Allocation By Period bar graphs are inconsistent.  

    150% takes up the whole bar (expected)
    100%  bar for the next period does not take up the whole space
    50% bar seems to take less than a third of the space

 

Expected Results: Allocation bar is displayed accurately and consistent. 

Actual Results:  Allocation bar is inconsistent in its display. 

Workaround: The numbers are still there, so this is easy to workaround. 

 

 

 

Environment

Release : 15.9.3

Component : CLARITY RESOURCE MANAGEMENT

Resolution

This is working as designed.

Across the same row, the height of all bars are RELATIVE to the MAXIMUM value. 

if you tried 200%, 150%, 100%, 50% -  expect it to show across the row the colored amount HEIGHT at 100%, 75%, 50%, 25% of the row height