Issue/Introduction

The Time Slicking job is running OK but I see an error messages in Data Warehouse section of the Health Report (Time Slices Setup / Monthly Slices).

What is the cause of this and how can it be fixed.

Environment

Release : 15.8.1,15.9,15.9.1,15.9.2,15.9.3

Cause

This is caused by a mismatch of Slice start date and number of periods for DWH enabled slices

Resolution

Make sure that Slice Start Date and Number of Periods for DWH enabled slices are the same to avoid this error in the health report

Additional Information

Starting in 16.0.0, there is no longer a requirement for the Fiscal time slice IDs to start on the same month.