Task owner blank creating from template

book

Article ID: 225491

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

Task owner is not copied over when creating new from template or Copying tasks from template. This is an issue both in Classic as well as MUX.

Steps to Reproduce: 

  1. Create a project: "My Template" 
  2. Add a task: "My Template Task" 
  3. Populate the Task Owner field 
  4. Mark the project as template 
  5. Create a new project from template using the Template created 
  6. On the project go to the Tasks tab 
  7. The template task copied 

Expected Results: Task Owner to be populated. 

Actual Results: Task Owner field is blank. 

Cause

DE62795 

Workaround: Manually add the Task Owner. 

Environment

Release 15.9.2 

Resolution

Fixed in Release 16.0.0