Tasks do not display in Gantt view when ID is first attribute

book

Article ID: 224948

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

You are not able to view the full Task list in Gantt view. Some tasks are displayed, but others are missing.

Environment

Release : 15.9.3

Resolution

Within Gantt the ID value was the first attribute, which was causing the issue. When Name was moved to the first attribute, it worked as expected.