ALERT: Some images may not load properly within the Knowledge Base Article. If you see a broken image, please right-click and select 'Open image in a new tab'. We apologize for this inconvenience.
Tasks do not display in Gantt view when ID is first attribute
book
Article ID: 224948
calendar_today
Updated On:
Products
Clarity PPM SaaSClarity PPM On Premise
Issue/Introduction
You are not able to view the full Task list in Gantt view. Some tasks are displayed, but others are missing.
Environment
Release : 15.9.3
Resolution
Within Gantt the ID value was the first attribute, which was causing the issue. When Name was moved to the first attribute, it worked as expected.